Applied Underwriters Grading Project
PROJECT SCOPE
Beginning in March of 2019, Valley Corporation completed a mass grading project for the insurance agency, Applied Underwriters. Valley provided the necessary amounts of fill material, then installed a surcharge for the massive foundation wall to be built on top of it. The installation of the surcharge was completed the same month as started and left in place to complete settlement.
MAJOR ITEMS OF WORK
- Mass grading
- 33,000 CY of frost removal prior to work
- 55,000 CY of fill for surcharge
Service Type: Grading
Owner: Applied Underwriters
General Contractor: Valley Corporation