Blair Sanitary Sewer
PROJECT SCOPE
Valley Corporation was hired by the City of Blair, NE to complete improvements upon its sanitary sewer system. This project was multifaceted, and in addition to the sewer improvements, required preparation of the sewer site, as well as the replacement of sidewalks and pavements. The project began in July of 2019 and was completed in October 2019.
MAJOR ITEMS OF WORK
- Installation of approximately 2,250 LF of 8 IN sanitary sewer and appurtenances
- 800 LF of horizontal directional drilling
- Replacement of sidewalks and pavements
Service Type: Utilities
Owner: City of Blair, Nebraska
General Contractor: Valley Corporation