245th Street Bank Stabilization

PROJECT SCOPE

Valley Corporation was hired by Douglas County to stabilize the bank of the East Bank of the Elkhorn River at 245th and Q Streets. Starting on March 22, 2019, beginning with tree removal and the use of imported soil and riprap, Valley was able to stabilize the banks with a clean, sturdy, dependable embankment. The project was finished and opened to the public on May 15, 2019.

 

MAJOR ITEMS OF WORK

  • Removal of 20 large trees
  • 8,550 CY of soil hauled in
  • 9,495 tons of riprap installed

 

Service Type: Stabilization

Owner: Douglas County

General Contractor: Valley Corporation